Payment Plan and Handover Schedule in a New Housing Project: The Buyer Checklist
An off plan purchase is a single signature that accepts two separate obligations. The buyer agrees to move money now and to receive a completed unit later. The wider the gap between those two events, the more weight two clauses carry: the payment plan, which decides what each instalment is tied to, and the handover date, which decides when and in what condition the unit changes hands.
This is not a sales page. It is the set of questions a buyer should have answered before signing, read against the framework that Turkish law sets for off plan residential sales in Articles 40 to 46 of Law No. 6502 on the Protection of Consumers. The aim is not to make a project look risky. It is to make the contract legible.
Two dates before any budget
A sales office usually opens with unit size and view. A buyer should open with two dates: the date the contract is signed and the date the unit is to be delivered. The distance between them sets how many instalments the plan can carry and how long the buyer lives with uncertainty.
The most common defect is a payment plan designed independently of the construction programme. Instalments fall due every month while none of them is tied to anything visible on site. The buyer then cannot tell what progress each payment purchased. A workable structure ties each tranche to a measurable stage: groundworks, structural frame, facade, fit out, pre occupancy completion.
Tying payments to stages is as much commercial discipline as legal design. A plan built that way gives both sides a shared measure when delay is discussed. Progress becomes something that can be shown with a site record, a supervision entry or a dated photograph rather than argued about.
Where the off plan regime begins
Article 40 defines the off plan residential sale as a contract in which the consumer pays the sale price in advance, in cash or in instalments, and the seller undertakes to transfer or deliver the property after the price has been paid in whole or in part. The key is money moving before delivery. The regime therefore attaches when the contract is formed, not when the first payment clears.
The same article requires a pre contractual information form, covering the points set by the Ministry of Trade, to be given at least one day before the contract is concluded. The third paragraph draws a hard line: no off plan residential sale contract may be made with consumers before a building permit has been obtained. In practice, the permit must exist and its scope must cover the unit being signed for.
Form requirements sit in Article 41. An off plan residential sale must be registered in the land registry, and a promise of sale must be executed in the form of an official instrument before a notary. The same article states that, absent a valid contract, the seller may not ask the consumer for payment under any name or take any document that places the consumer under an obligation. The buyer's first question is therefore not the price but which instrument and which registration secure it.
Mapping instalments to stages
A payment plan binds when it is part of the contract. That means it belongs in a schedule that carries, on every line, the due date, the share of the price and the construction stage it is tied to. A buyer should ask for three things before signing: a written definition of each stage, progress reporting by an independent supervision body, and a written rule for how the schedule behaves if a stage slips.
Tranche | Tied to | Evidence a buyer should request |
Down payment | Contract and land registry registration | Registration record and pre contractual information form |
Second tranche | Foundations and basement complete | Dated site record with photographs |
Third tranche | Structural frame and floor slabs | Building supervision entry |
Fourth tranche | Facade and roof waterproofing | Progress report |
Final tranche | Handover and occupancy process | Occupancy permit |
The last line is the one that matters most. Taking the final tranche before handover means the buyer gives up the only leverage held in reserve. Tying the last payment to handover, or to the official step that accompanies it, turns the plan into a real timetable.
The statutory ceiling on the handover date
Article 44, as amended in 2022, requires the off plan unit to be delivered within the period undertaken in the contract and states that this period may in no case exceed forty eight months from the contract date. The same article adds that, where the construction easement has been registered in the land registry in the consumer's name together with transfer of possession, transfer and delivery are deemed to have been made.
That last sentence sits at the centre of most handover disputes. Buyers tend to treat key handover as delivery. The law also treats registration of the construction easement and transfer of possession as delivery. The same word therefore carries two meanings across the table. Defining delivery in one sentence inside the contract closes most of that gap before it opens.
Three details matter when reading the date. Whether it is written as a calendar date or left as a reasonable period after the occupancy permit. Which notification route applies if the date slips. And whether the events that count as outside the seller's control are listed. Without those three, a date is written but the timetable does not run.
What the buyer can do if handover slips
The options open to a buyer are defined in the law and they are not interchangeable. The right of withdrawal sits in Article 43: within fourteen days the consumer may withdraw for any reason, without penalty, and it is enough that notice reaches the seller within that period. The burden of proving that the consumer was informed about the right lies with the seller.
Termination is a separate regime in Article 45. The consumer may terminate for any reason up to twenty four months from the contract date. On termination the seller may claim the taxes, duties and similar statutory costs, together with compensation that steps up with elapsed time. The bands in the statute start at two percent of the contract price for the first three months and reach eight percent between twelve and twenty four months.
The second paragraph of the same article states that where the seller has not performed its obligations at all or as required, the seller may not claim any amount from the consumer. Where the delay is attributable to the seller, that provision closes the compensation argument at the outset. What a buyer should ask for at that point is a written statement of the cause of delay and the date it began.
The security question
Article 42 requires a seller, for projects above a size threshold set by the Ministry by reference to unit count or total project value, to obtain completion insurance before starting off plan sales, or to satisfy other security and conditions set by the Ministry. The same article provides that compensation, security and similar guarantees under that cover cannot be included in a bankruptcy or liquidation estate, cannot be attached, and cannot be subject to interim injunctions.
For a buyer this is a document request, not an abstraction. Which instrument applies, which project and which units the policy or guarantee covers, and whether its validity runs past the handover date. The existence of a security is not enough on its own. Its scope has to match the contract being signed.
Keeping the construction record
Signing the plan does not end the buyer's work. Progress tracking also determines when each tranche falls due. A buyer should know in advance which document to request at each stage. Supervision records, site minutes, progress reports and finally the occupancy permit form that chain.
The last link connects to a second subject. Once the occupancy permit is issued, the transition from construction easement to condominium ownership comes into play, and that transition changes the buyer's position in the land registry. Anyone tracking a payment plan also needs to know which step remains after handover.
FAQ
When is the first payment made in an off plan sale?
The law bars the seller from requesting payment before a valid contract exists. The first payment therefore follows conclusion of the contract and delivery of the pre contractual information form. Giving that form at least one day before signature is a separate requirement.
What if the contract has no handover date?
The handover date is part of the mandatory content of an off plan residential sale contract, and the statute caps the period at forty eight months. A contract without a date removes the buyer's strongest point of reference. Ask for a calendar date before signing.
Can the payment plan be changed later?
Once the plan is part of the contract, it can only change by written agreement between the parties. A unilateral revision of the timetable by the seller does not by itself accelerate the buyer's obligation. When such a request arrives, ask for the written reason and the revised schedule.
Is withdrawal the same as termination?
No. Withdrawal is a fourteen day right and carries no penalty. Termination may be exercised for up to twenty four months and is subject to the staged compensation regime in the statute. The notice should state plainly which right is being exercised.
Does registering the construction easement count as delivery?
Article 44 provides that, where the construction easement is registered in the consumer's name together with transfer of possession, transfer and delivery are deemed to have been made. The contract should therefore define delivery in a single sentence that names the step.
External sources
Law No. 6502 on the Protection of Consumers, Articles 40 to 46: https://www.mevzuat.gov.tr/MevzuatMetin/1.5.6502.pdf
Law No. 6502, record in the Turkish legislation database: https://www.mevzuat.gov.tr/mevzuat?MevzuatNo=6502&MevzuatTur=1&MevzuatTertip=5
The content of the pre contractual information form referred to in Article 40 is set by the Ministry of Trade: https://ticaret.gov.tr
Sources were accessed on 19 November 2026. Confirm the consolidated text in force on the transaction date, the scope of the project's building permit, and the current validity of any security offered by the seller.
A restrained next step
For a buyer already holding a payment plan, the fastest control is a single sheet with two columns. List the tranches on the left. On the right, write the construction stage each tranche is tied to and the document that proves that stage. The number of empty rows is the number of questions to ask before signing.