From Construction Easement to Condominium Ownership: Steps at Project Handover
A buyer who receives a title deed reading construction easement has usually read it correctly and drawn the wrong conclusion. Construction easement is not a temporary flaw. It is the right that Turkish law creates over an unfinished building, attached to a land share, and designed from the outset to convert into condominium ownership once the building is complete.
The conversion is a file, a permit and a registration. This note sets out what the transition depends on, which documents the land registry asks for, who may start the process, and what actually changes for an owner afterwards. The framework is the Condominium Law No. 634, with the delivery definition in Article 44 of Consumer Protection Law No. 6502 sitting alongside it.
The difference in one sentence
Condominium ownership divides a building into independent units, each of which is a separate piece of immovable property. Construction easement is the earlier stage: a right attached to a land share, created before or during construction, intended to be converted later. Article 3 of Law No. 634 states the relationship directly. Construction easement is a type of easement attached to a land share and, on the basis of the occupancy permit issued for the whole building, it is converted into condominium ownership ex officio, subject to the conditions the law sets out.
Two words in that sentence matter. The basis of the conversion is the occupancy permit. And the conversion is ex officio, meaning it does not depend on a separate declaration of intent from the parties. In practice this does not mean the entry appears by itself. The land registry can only act once the file is complete.
The occupancy permit is the gate
The occupancy permit is the document issued by the competent administration confirming that a building has been completed in line with its approved project. The whole timetable of the conversion hangs on its date. Without it, condominium ownership cannot be established, because the statute ties the conversion directly to that permit.
For a buyer this produces a concrete question to ask before handover. Has the occupancy permit been issued, on what date, and which buildings does it cover. Where a project is phased, each phase generates its own permit and its own conversion. The scope of the permit by block or phase therefore decides which step the buyer waits for, and when.
Issuance of the permit has a second consequence. In off plan residential sales, Article 44 of Law No. 6502 allows delivery to be established through registration of the construction easement in the consumer's name together with transfer of possession. Delivery is therefore not always key handover. That distinction belongs in the contract as a single sentence, because it drives both the payment plan and the conversion timetable.
Ex officio conversion and the right to apply
Article 3 of Law No. 634 also provides that the conversion may be carried out at the request of the landowner or even at the request of one of the co-owners holding a construction easement. That provision resolves a familiar deadlock. Where a project has several owners and some of them do not move, a single easement holder can start the process.
The practical reading is that conversion is not conditional on a unanimous decision. Completing the file still depends on assembling the project and management plan documents, which is a collective effort. The sequence normally runs as follows. The occupancy permit is obtained, the approved architectural project and the management plan are transmitted to the land registry in electronic form, and the official instrument is then executed and registered.
What the land registry file contains
Article 12 requires the owner of the main property, or all co-owners, to apply to the land registry and to attach two documents. The first is the architectural project prepared by the project architect, showing the measurements, position and land shares of the independent units, their type and sequential number, and the construction area, approved by the competent public authorities and transmitted to the land registry in electronic form. The same subparagraph includes the occupancy permit as part of that file.
The second is the management plan, prepared under Article 28 according to how the units are to be used and, where there are several buildings, according to their character, signed by the owner or owners establishing the condominium.
The management plan is the item most often missing. A plan prepared at the start of a project can fall out of step with later changes to shared areas. The land registry looks for consistency between the use described in the plan and the unit definitions in the project. A mismatch between those two documents stops the conversion on a technical point rather than a legal one.
No second management plan at conversion
Article 14 requires the management plan to be filed with the land registry when the construction easement is created, and adds a clear simplification. A separate management plan is not requested at the transition to condominium ownership.
That answers a question that comes up at almost every handover. If the management plan was filed when the easement was created, it does not have to be produced again for the conversion. The simplification does not certify that the content is current. Where the use of shared areas, parking allocation or the number of commercial units has changed since, updating the plan becomes a separate exercise.
Official instrument, registration and what follows
Article 13 provides that, once the registrar is satisfied that the documents are complete and properly executed and that the applicants are authorised, the registrar draws up the official instrument establishing condominium ownership. That instrument also counts as the application for registration.
The article then describes the effect in detail. A note that ownership has been converted to condominium ownership is entered on the page where the construction easement was recorded, and that page is closed to transactions other than easement rights. Each independent unit is registered on a separate page of the condominium register together with its land share, and the registers are cross referenced. Each unit registered in the condominium register acquires the status of a separate immovable property and takes the number shown on its approved plan.
For an owner the change is concrete. Before conversion the holding is a right attached to a land share. After conversion it is a unit with its own number, its own land share and its own register page. Later transactions, whether a charge, a promise of sale or a lease, run through that new page.
What changes after conversion
Conversion also brings the management relationship into force. Maintenance of shared areas, apportionment of expenses, meetings and decision procedures fall under the second and third sections of the statute. Expenditure incurred during the easement period is a separate ledger question and is one of the most frequently disputed items at handover.
A financial reconciliation should therefore accompany the conversion file. Contributions collected during the easement period, shared expenses incurred, and the balance carried forward. That reconciliation shows the first management meeting of the new period exactly what was taken over. A balance transferred without documentation tends to become the objection raised in later years.
Handover checklist
Stage | Document or step | From whom |
Building complete | Occupancy permit | Municipality or competent administration |
Project file | Approved architectural project, electronic submission | Land registry and project architect |
Management | Management plan under Article 28 | Owner or owners |
Registry step | Official instrument and application for registration | Land registry |
Afterwards | Condominium register page and land share | Land registry |
Financial | Reconciliation of easement period contributions and expenses | Management and owners |
Until the first row is complete, none of the others can start. At handover the first document to request is therefore the occupancy permit, not the key. Key handover may appear in the contract as a form of delivery, but the document that changes the registry position is the permit.
Where a unit is mortgaged, the land registry may ask for additional documents and the conversion proceeds with the lender's knowledge. If a mortgage is in place, a written reconciliation with the lender before the conversion date tends to shorten the process.
FAQ
Who applies for the conversion to condominium ownership?
The statute sets the application by the owner of the main property or all co-owners, while also allowing the conversion to be carried out at the request of one co-owner holding a construction easement. That prevents the process from stalling on one party's inaction.
Can the conversion happen without an occupancy permit?
No. The statute bases the conversion of the construction easement on the occupancy permit issued for the whole building. A condominium registration without that permit has no foundation.
Is every owner's signature required?
Assembling the file is a collective effort, but the application can be started by a single easement holder. The management plan, however, must be signed by the owner or owners, as Article 12 requires.
What happens to contributions paid during the easement period?
They should be captured in a written reconciliation at conversion. Contributions collected, shared expenses incurred and the balance carried forward should be presented at the first management meeting of the new period.
What changes in the land registry after conversion?
Each unit is registered on a separate page of the condominium register and acquires the status of a separate immovable property. The page of the main property is closed to transactions other than easement rights, and the registers are linked.
External sources
Condominium Law No. 634, Articles 3, 11, 12, 13, 14 and 28: https://www.mevzuat.gov.tr/MevzuatMetin/1.5.634.pdf
Law No. 634, record in the Turkish legislation database: https://www.mevzuat.gov.tr/mevzuat?MevzuatNo=634&MevzuatTur=1&MevzuatTertip=5
Consumer Protection Law No. 6502, Article 44 on the delivery definition in off plan sales: https://www.mevzuat.gov.tr/MevzuatMetin/1.5.6502.pdf
Sources were accessed on 19 November 2026. Confirm the consolidated text in force on the transaction date, the scope of the occupancy permit, and the current document requirements of the land registry office.
A restrained next step
Put the conversion file on one page. On the top line, record the date of the occupancy permit and the blocks it covers. Below it, list the approved architectural project, the management plan and the date of the official instrument. Whichever line is empty shows where the conversion is waiting.